Arnish Point Re-cladding

Name: Arnish Point Re-cladding
Location: Stornoway, Lewis
Duration: 6 Months
Scope: Installation of Tension Netting and Vertical Weather Protection

Arnish Point Re-claddingArnish Point Re-claddingArnish Point Re-cladding

Arnish Point Re-cladding

Geckotech Solutions Ltd were contacted by our client who was tasked with the challenge of re-cladding and re-roofing the huge Arnish Point Fabrication Yard in Stornoway, Lewis. Our client required an innovative approach to provide access, dropped object and weather protection to his men and the inhabitants of the fabrication shop whilst this project was ongoing.

Due to the busy nature of the fabrication shop floor and the operation of the 3 large cranes inside traditional methods of access were not going to be suitable. The solution was to install 5000 SQM of tension netting systems to follow the profile of the existing roof. This system provided walk on capability to the third party roofers and dropped object protection to the work force below. The system was installed quickly causing little or no disruption to the building and provided safe unhindered access to all who used it.

Geckotech also installed weather and debris containment measures to the elevations of the structure in readiness for the re-cladding work. This vertical protection was installed quickly and capable of with standing the consistently strong winds and wet weather.  

Back to Projects

Recent Projects

Name: Forth Rail Bridge
Location: S Queensferry
Duration: 3 Years
Scope: Provision of Industrial Rope Access Services Bridge Wide

Continued >>

Location: UK Wide
Duration: 5 Years
Scope: Provision of Access Support and Examination Services

Continued >>

Name: Arnish Point Re-cladding
Location: Stornoway, Lewis
Duration: 6 Months
Scope: Installation of Tension Netting and Vertical Weather Protection

Continued >>

Name: Kingsmead Leisure Centre
Location: Canterbury
Duration: 4 weeks
Scope: Maintenance & Repair of Glazed Curtain Walling.

Continued >>

Name: Totem
Location: Ocean Terminal Edinburgh
Duration: 4 weeks
Scope: Installation of Totem Support System

 

Continued >>

Name: Tay Bridge Inspection Project
Location: Tay Rail Bridge
Duration: 6 months
Scope: Rescue Cover, Tension Netting Systems and Access Consultancy

Continued >>

Name: Marks Hotel Re-Coating Works

Location: Bath Street, Glasgow

Duration: 4 weeks

Scope: Re-coating/ sealing of exisitng rough cast render

Continued >>

Are you looking for something?